1. COMPETITION >
  2. DETAILS

公告进程时间:2023-09-01

nhai Stone Park (Dachan Bay Section) is located in the core area of Guangdong, Hong Kong and Macao Bay Area - Dachan Bay Area of Qianhai Cooperation Zone, which is an important part of the spatial structure of Qianhai " "one bay, two belts, five area and five green corridors"", and is in the visual center of Qianhai Bay. The project site is adjacent to Shenzhen "Internet +" Future Science and Technology City (hereinafter referred to as Future Science and Technology City) under construction, starting from Weiyi Road in the north and ending at Weixi Road in the south, with the seashore on the east side, adjacent to Jing'er Road on the west side.

Location Map

Work Content

The land scope of the Qianhai Stone Park (Dachan Bay section) includes three units of the DY-02  in Shenzhen's ‘Internet +’ Future Science and Technology City, with a total land area of approximately 186,001 m²: DY02-01-01 (G1 Parkland) with a land area of 146,828.47 m², DY02-01-02 (E1 Water Area) with a land area of 6,793.49 m², DY02-02-01 (G1 Parkland) with a land area of 32,379.35 m². The design scope is limited to the area within the 2022 coastline, primarily focusing on the design of the two park green spaces, DY02-01-01 and DY02-02-01, without any construction activities in the sea. (The final figures are subject to approval by the competent authority.)

Project scope (the base map is the land use planning map of Shenzhen's Internet +’ Future Science and Technology City Control Detailed Planning)

Project scope (the base map is the land use planning map of Shenzhen's Internet +’ Future Science and Technology City Control Detailed Planning)



Site Existence

The existing conditions within the design scope consist of a regularly shaped open area with relatively flat terrain. The eastern and southern boundaries of the site are adjacent to the sea. The eastern boundary features a coastal shoreline with a mangrove belt primarily composed of Rhizophora stylosa. The southern boundary is defined by Weiliu Road and is in close proximity to the sea. The western faces Jing'er Road and the ongoing construction of Future Science and Technology City projects 04 and 05 blocks. The northern boundary is characterized by existing green spaces.

Site Existence




Project Positioning

The Qianhai Park Cluster is an important component of Shenzhen's "Mountains and Seas Connecting the City" initiative, specifically part of the "one belt" (Coastal blue landscape belt). It plays a crucial role in achieving deep integration between the park and the city, connecting the slow urban spaces around Qianhai Bay. The Qianhai Stone Park (Dachan Bay section) serves as the visual centerpiece of the coastal skyline in the Qianhai Park Cluster, particularly in the bay area.

Location map of this project within the spatial layout of Shenzhen's ' Mountains and Seas Connecting the City ' plan.


The Qianhai Stone Park (Dachan Bay Section) will leverage the industrial characteristics of the Future Science and Technology City to create a differentiated construction of comprehensive parks integrating culture, leisure, and ecology. It aims to establish a dynamic coastal space for technological innovation and vitality.



Overall design objectives

Implementing the Qianhai Stone Park "One Ring and Five Corridors" planning structure aims to create a comprehensive public space system with elements of "mountain, sea, forest, city, island, and harbor" integrated. Combining the urban development needs and leisure lifestyles of the residents in this area, the project's spatial structure, planning layout, and spatial volume are studied with an international and forward-looking development perspective. It considers the overall planning of the surrounding development zones to create a unique urban water system and green open space. This will create a vibrant waterfront city integrating ecology, landscape, culture, art, and technology.



Construction Contents

The main construction contents include park landscaping, park greening, pedestrian overpass with landscape features, supporting building construction, special projects (mangrove ecological restoration), park supporting water and electricity, and intelligent engineering.

Tender controlling price
The tender controlling price of this project is set at ¥7,024,500.00.



Work content

The work after awarding includes: pre-conceptual design and main design coordination work, feasibility study report preparation, conceptual design, post-service, coordinated integration, relevant special consulting co-ordination, and post-assessment of the project, ect.

Registration Requirements

  • The applicant must be an independent legal entity or organization registered within the territory of the People's Republic of China or abroad.

  • Consortium bidding is not accepted for this project.

  • There are no qualification requirements for the project manager.

Work Rules

The project adopts an “open bidding” procedure, divided into the Pre-qualification, bidding, and final evaluation stages. Please refer to the Pre-qualification documents for details.

Stage

Date

item

pre-qualification

1st Sep. 2023

Release the announcement

and accept registrations

By 17:00, 8th Sep. 2023

Deadline for Questions

By 17:00, 13th Sep. 2023

Q&A and Addendum Release

By 18:00, 18th Sep. 2023

Deadline for submission of pre-qualification application

25th-28th Sep. 2023

Pre-qualification review and result announcement

9th-11th Oct. 2023

Applicants submit the Bid Confirmation Letter.

Bidding

28th Sep. 2023

The bidding documents are now being released.

13th Oct. 2023

Site survey and Q&A meeting

By 17:00, 30th Oct. 2023

Deadline for Questions

By 17:00, 6th Nov. 2023

Q&A and Addendum Release

By 15:00, 13th Nov. 2023

Applicants submit bidding documents.

15th-17th Nov. 2023

Design review meeting

Final Evaluation

27th Nov. 2023

Final Evaluation

28th -30th Nov. 2023

Announcement of the results

Note: All the time mentioned above is UCT+8. The above schedule is for reference only. The final "Shenzhen Transaction Group Limited (Shenzhen Public Resources Trading Centre)" announcement time shall prevail, and the tenderee reserves the right to adjust the schedule.

Compensation

Ranking

Compensation
( RMB, 10,000, all inclusive of tax)

Note

1st

0

Award of contract

2nd

60

 

3rd

60

4th

40

5th

40

1)Payment of compensation for bid loss and related fees

The compensation for this tender shall be paid in RMB, including tax. The applicants shall provide the payment request information as required by the tenderee. And the compensation shall be paid by the tenderee.

2)Others

The applicants must complete the formal bidding process of the project in accordance with the requirements of the tender document and pass the review of the bid review committee before receiving the compensation; otherwise, compensation will not be given. The tenderee has the right to re-bid according to the project's situation, and all applicants can participate in the tender again. The intellectual property rights of the compensated programs shall be enjoyed by the tenderee except for the right of authorisation, and the tenderee shall have the right to use them for reference in the program implementation without compensation.



Announcement and Document Download

The pre-qualification documents can be downloaded from the “Shenzhen Public Resource Trading Center”.

The final information shall be subject to the tender announcement / tender document issued by “Shenzhen Public Resource Trading Center”.

To view the announcement and download the pre-qualification documents (click “read more” at the bottom of the article to visit):

Tenderee:

Shenzhen Qianhai Construction & Investment Holdings Group Co., Ltd

Consultant and Agency:

RJRX Urban Planning & Design Consultants Co.Ltd., Shenzhen

Tendering Enquiry:

Mr Chen (Technical), Tel. +86-13590282124

Ms Li (Business), Tel. +86-13632658134

 (UTC+8 9:00-12:00, 14:00-18:00 Business day)