The project is located in the No.07 and No.08 neighborhoods of Unit No.19 in Qianhai, Shenzhen, an area enclosed by Yihai Avenue, Qianhwanhe West Street, Moon Bay Avenue, Zimao East Street, Tonggang Street and Mawan First Road.

The project enjoys an abundance of high-quality landscape resources such as mountain scenery, seaside, park and river, together with well-established infrastructures and convenient transportation. And with that, it promises to help Qianhai evolve into a globalized highland of industries, creating opportunities for talents from home and abroad, building world-class, high-end residential community and a new center of luxurious communities in Qianhai, and setting up a pilot demonstration community with characteristics of socialism for Guangdong-Hong Kong-Macao Greater Bay.

Work Content

1.The tender applies to the general design contracting throughout the whole process, covering the first phase for 19-07-02 and 19-07-03 plots, second phase for 19-07-05 plot, and third for 19-08-03 plot.

2.The design work for each phase should include schematic design and design development(including budget estimate), preliminary design (including budget estimate), construction drawing design, cooperation between the construction team and tenderee, cooperation between the design and construction teams, completion of as-built drawing, general design contracting, etc. Design drawing for each phase shall comply with applicable regulations and requirements of Qianhai Administration Bureau, Shenzhen Municipal government and central government. The bidder shall complete all works phase by phase and make any modification arising from the review by government authorities according to the terms of the tender document.

Registration Requirements

1. The bidding adopts open application, soliciting excellent bids from across the world, and the number of joint groups should be no more than 3. The bidders should be registered enterprises inside or outside the People's Republic of China. The domestic bidder undertaking preliminary design, construction drawing design, and general contracting management (including subdivision design) should have Class A or above building (building engineering) qualification issued by the government administrative authorities; and it shall be the leading member while bidding as a joint group.

2. And individuals are unaccepted.

3. Members of joint group should not re-apply for the bid independently in the name of their own or other joint group constituted with other design institutes, nor may they participate in the bidding in as a consultant.

4. The bidder should submit the deliverable in compliance with the Design Brief and the conceptual proposal in accordance with the requirements of the international tender document for the project.

Work Rules

Three Phases of Tender Process:

Phase 1:Open Application And Conceptual Proposal Design;

Phase 2:Bid Evaluation;

Phase 3:Bid Determination

Tender Schedule

Time

Item

Phase 1

Open Application

 And Conceptual Proposal Design

09:00, May 21, 2020

Issuance of prequalification notice and acceptance of application

17:00, June 1, 2020

Q & A in writing (by mail )

17:00, June 3, 2020

Deadline of Q&A

17:00, June 5, 2020

Deadline for the submission of prequalification documents

17:00, June 8, 2020(Planning

Prequalification evaluation meeting

17:00, June 12, 2020(Planning

Issuance of entry list and Finalist Notice

Phase 2

Bid Evaluation

17:00,June 15, 2020(Planning

The submission of Bidding Confirmation Letter; site Survey, Q&A, project kick-off meeting; issuance of final planning condition and any other supplementary documents of Design Brief

17:00, June 13-30, 2020(Planning

Q & A in writing (by mail or fax)

July28, 2020 (48days,Planning)

The submission of design scheme

July29,2020(Planning

Select 3 candidates to enter bid determination phase after evaluation

Phase 3   Bid Determination Meeting

July30,2020(Planning

Determination of the awarded bidder

Announcement of Result

August,2020Planning

Announcement of the awarded bidder


Prizes

Tender price is controlled at: RMB 50.3 million. The unit price (calculated by GFA above ground) is controlled at RMB 264.66 per square meter. And the costs for schematic design, design development (preliminary architectural design development) and construction coordination shall not exceed 50% of the total controlled price.

Compensation:

 

Amount (Unit: RMB )

Notes

Awarded bidder

Contract awarding

Tax included

The second place winner

RMB 1.5million

the third place winner

RMB 1.2 million

3 bidders passing the second phase but not the bid determination phase.

RMB 1million for each

Notes: The tenderee is entitled to not pay design compensation once evaluation experts consider that the depth and quality of the bidding proposal fail to meet the requirements.


Host: Shenzhen International Qianhai Investment and Management (Shenzhen) Co., Ltd.

Organizing agent(s) :ATU China

Contact:0755-86250922; guanzhusz@atuchina.com